(v0.1 - Initial creation for review) |
(v0.2 - Amended to show that a separate webservice will be used if an entire job is cancelled) |
||
Line 5: | Line 5: | ||
|Supimix_Client_Reference= | |Supimix_Client_Reference= | ||
|Supimix_Number=324096 | |Supimix_Number=324096 | ||
|The_version_of_the_document=0. | |The_version_of_the_document=0.2 | ||
|Your_Name=A N Walker | |Your_Name=A N Walker | ||
|Supimix_PO_Reference= | |Supimix_PO_Reference= | ||
Line 46: | Line 46: | ||
The new Pall-Ex Export process will work as follows: | The new Pall-Ex Export process will work as follows: | ||
At least 2 messages will be sent to update the Pall-Ex TWINE system, by connecting through | At least 2 messages will be sent to update the Pall-Ex TWINE system, by connecting through three methods of their existing webservice: | ||
* AddEpodPallet – One message sent per pallet on the consignment, to update a pallet and consignment with delivery and signatory information. | * AddEpodPallet – One message sent per pallet on the consignment, to update a pallet and consignment with delivery and signatory information. | ||
* AddEpodConsignment – One message sent per cancelled consignment, to update the consignment as cancelled delivery, with an appropriate reason code. | |||
* AddMPodImage – to upload the signature image from the delivery to the consignment. | * AddMPodImage – to upload the signature image from the delivery to the consignment. | ||
The process will check the responses of sending these messages to the webservice, and will store the results in the Audit tables within ''CALIDUS'' ePOD. Messages that process in error will be marked as such, so that they may be identified and reprocessed manually if required. | The process will check the responses of sending these messages to the webservice, and will store the results in the Audit tables within ''CALIDUS'' ePOD. Messages that process in error will be marked as such, so that they may be identified and reprocessed manually if required. | ||
Line 55: | Line 56: | ||
|Functional_Specification_Days=1.75 | |Functional_Specification_Days=1.75 | ||
|Technical_Specification_Days=1.25 | |Technical_Specification_Days=1.25 | ||
|Development_Days=6 | |Development_Days=6.5 | ||
|Testing_and_Release_Days=1.25 | |Testing_and_Release_Days=1.25 | ||
|Implementation_Days=1 | |Implementation_Days=1 |
Revision as of 11:34, 24 March 2015
![]() |
CHANGE REQUEST ESTIMATE |
Client | PART | Project | DEV | Site | PART |
Client Reference | Aptean Reference | 324096 | Estimate Version | 0.2 | |
Prepared By | A N Walker | Estimate Date | 13/03/2015 | ||
Invoice Reference | Priority | 3 | |||
Customer | AE Parker | System Version | 1.X |
Client Request |
AE Parker will be rolling out CALIDUS ePOD to their fleet and will need to send ePOD information/confirmation on deliver completion through to Pall-Ex systems. |
Aptean Solution |
![]()
At least 2 messages will be sent to update the Pall-Ex TWINE system, by connecting through three methods of their existing webservice:
|
![]() | Unknown costs for client/year (PART/2015) |
Cost Details | |||
Activity | Hours | Rate per hour (£) | Cost (£ Exc. VAT) |
Requirements | 0.00 | 0.00 | £0.00 |
Change Request Evaluation | 1.00 | 0.00 | £0.00 |
Functional Specification | 1.75 | 0.00 | £0.00 |
Technical Specification | 1.25 | 0.00 | £0.00 |
Development | 6.50 | 0.00 | £0.00 |
Testing and Release | 1.25 | 0.00 | £0.00 |
Implementation | 1.00 | 0.00 | £0.00 |
Project Management | 0.75 | 0.00 | £0.00 |
TOTAL | 13.50 | £0.00 |
Estimate excludes training, release to live and go live support. |
Copyright © Aptean 2015. |