EST 333704 NHSBT Default Time on Inter-centre Moves
From Calidus HUB
![]() |
CHANGE REQUEST ESTIMATE |
Client | NHS | Project | DEV | Site | NH-ALL |
Client Reference | CR-Feb16-03 | Aptean Reference | 333704 | Estimate Version | 0.1 |
Prepared By | A N Walker | Estimate Date | 29/02/2016 | ||
Invoice Reference | Priority | 3 | |||
Customer | System Version | CTMS: 11.X |
Client Request |
Default the times of Inter-centre Moves when received from Pulse. |
Aptean Solution |
An issue exists within Pulse whereby inter-centre moves on BMVs are generated as separate orders, and also the collection and delivery times are not set appropriately. This is leading to planning issues within C-TMS, and forcing manual changing of delivery times onto the operation.
The C-TMS inbound order interface will be modified to check the collection and delivery dates of all inter-centre movements (i.e. where the From and To Location Types are RDC). In this case, the system will check for any fixed routes set up in the system that are appropriate for those locations. If found, the process will modify the times of these moves so that they can be automatically or manually planned without further manual intervention on the times. The Order Type will be set to "I", and the Delivery Type changed to "Inter-Centre", a new delivery type in the system, to make it clear that these orders have been modified. |
![]() | Unknown costs for client/year (NHS/2016) |
Cost Details | |||
Activity | Hours | Rate per hour (£) | Cost (£ Exc. VAT) |
Requirements | 0.00 | 0.00 | £0.00 |
Change Request Evaluation | 1.25 | 0.00 | £0.00 |
Functional Specification | 1.00 | 0.00 | £0.00 |
Technical Specification | 0.00 | 0.00 | £0.00 |
Development | 2.50 | 0.00 | £0.00 |
Testing and Release | 0.50 | 0.00 | £0.00 |
Implementation | 0.50 | 0.00 | £0.00 |
Project Management | 0.25 | 0.00 | £0.00 |
TOTAL | 6.00 | £0.00 |
Estimate excludes training, release to live and go live support. |
Copyright © Aptean 2016. |