EST 350226 JBG Hide spare job or prevent update
![]() |
CHANGE REQUEST ESTIMATE |
Client | JBG | Project | DEV | Site | DEV |
Client Reference | Aptean Reference | 350226 | Estimate Version | 0.1 | |
Prepared By | A N Walker | Estimate Date | 1/5/18 | ||
Invoice Reference | Priority | 3 | |||
Customer | Oak Furnitureland | System Version | 4.X |
Client Request |
A method is required that prevents the 2nd job (the 'spare job') on the device from being seen by (or if not, updated by) the user until it is updated with products. |
Aptean Solution |
Loads are being sent to CALIDUS ePOD from the ERP with an additional job on them (a 'spare' or empty job). This is there to hold open the load when all normal jobs are complete, so that the ERP can send in additional jobs for the load if required (for shortages on prior deliveries, or late receipts for the day).
The issue is that the drivers have been completing these jobs before day-end, meaning that additional jobs cannot be set to the device on those loads.
|
![]() | Unknown costs for client/year (JBG/2018) |
Cost Details | |||
Activity | Hours | Rate per hour (£) | Cost (£ Exc. VAT) |
Requirements | 0.00 | 0.00 | £0.00 |
Change Request Evaluation | 0.25 | 0.00 | £0.00 |
Functional Specification | 0.50 | 0.00 | £0.00 |
Technical Specification | 0.00 | 0.00 | £0.00 |
Development | 2.75 | 0.00 | £0.00 |
Testing and Release | 0.50 | 0.00 | £0.00 |
Implementation | 0.25 | 0.00 | £0.00 |
Project Management | 0.25 | 0.00 | £0.00 |
TOTAL | 4.50 | £0.00 |
Estimate excludes training, release to live and go live support. |
Copyright © Aptean 2018. |